Bridge load refers to the collective term for various possible loads that should be considered in the design of bridge structures, including dead load, live load, and other loads. This includes live loads on railway trains or road vehicles, as well as the impact forces, centrifugal forces, lateral sway forces (railway trains), braking or traction forces, crowd loads, and soil pressure generated by train vehicles. Bridge load test is a relatively intuitive method for evaluating the bearing capacity of bridges.
Why is it necessary to conduct load tests on bridge structures? What is the purpose and significance of load testing?
For newly built bridges, load tests are conducted to verify the design and construction quality of the bridge span structure, determine the reliability of the project, provide reliable basis for the smooth operation of the bridge, and provide complete initial fingerprint data for long-term monitoring of the bridge. It also accumulates measured test data for the design and construction of similar bridges. Especially for bridges with large spans and complex structures, it is an important means of acceptance and quality assessment. Through load testing, the construction quality and structural stress performance of bridges can be inspected, and the actual operating conditions and usage conditions of bridges can be determined, providing scientific basis for completion acceptance and operation.
1、 Purpose of Bridge Load Test
Bridge load test is an identification method that directly tests the working state of bridge structures. Due to the large span of the bridge, the design and construction technology are difficult. In addition, according to relevant national regulations, large-scale bridges should undergo production appraisal tests after completion. The bridge load test aims to achieve the following objectives:
1. Through on-site loading tests and comprehensive analysis of experimental observation data and phenomena, the design and construction quality of this bridge are inspected, the reliability of the project is determined, and technical basis is provided for completion acceptance;
2. Directly understand the actual working status of the bridge span structure, determine its actual bearing capacity, and evaluate its performance under the designed load;
3. Verify the correctness and rationality of design theories, calculation methods, and various assumptions in the design, providing experience and accumulating scientific data for the design and construction of similar bridges in the future;
4. By conducting dynamic load tests to determine the inherent vibration characteristics of the bridge span structure and its dynamic performance during long-term service load stages, evaluate the actual dynamic load performance of the structure;
5. Establish a bridge health model through load testing and record the health parameters of the bridge.
2、 Classification of Bridge Load Tests
Bridge load tests include static load tests and dynamic load tests. In general, only static load tests are conducted, and if necessary, partial dynamic load tests may be added, such as for extra large bridges, new bridges, etc.
Static load test is a process in which vehicles are parked on a bridge to detect the actual internal forces and deformations of key structures such as the main tower, main beam, and diagonal cables of the bridge, in order to determine the working state of the bridge structure under static load. It refers to applying a static load to a designated position on the bridge to test the static strain, displacement, and cracks of the structure, and infer the working state and service capacity of the bridge structure under load.
Dynamic load test refers to the use of dynamic loads, such as driving vehicle loads or other dynamic loads, on bridge structures to determine the state of the bridge during vehicle movement, in order to measure the dynamic characteristics of the structure, such as vibration deformation. Through this test, a comprehensive inspection of the bridge is carried out to determine whether the weight limit of each part meets the design requirements, providing a health assurance report for the delivery and acceptance of the bridge, ensuring the safety of vehicle passage, and thus determining the impact and vibration effects on the bridge structure under dynamic loads.
The dynamic load test and static load test of bridges have their own characteristics. Firstly, the amplitude generated by the structure (such as vehicles, crowds, gusts, or seismic forces) and the vibration effects of the structure vary over time, and the response of the structure under dynamic loads is closely related to the dynamic characteristics of the structure itself. The dynamic effects generated by dynamic loads are generally greater than the corresponding static effects.
So, what kind of bridge requires load testing?
During the completion and acceptance of new bridges, as well as the maintenance, reinforcement, renovation, and expansion of old bridges.
When a bridge reaches its designed service life and needs to continue serving.
When the bridge is damaged and its bearing capacity cannot be determined.
4. Other situations that require testing of relevant bridge mechanics indicators.
What should be noted in bridge load testing?
After the completion of super large bridges and structurally complex bridges, the contractor shall assist and cooperate with the owner to conduct load tests on the bridge or a certain part of the bridge to verify that the structure has sufficient capacity to withstand the design load.
2. The load test shall be conducted by a qualified scientific research or design unit commissioned by the owner.
3. The bridge load testing items shall be in accordance with the drawings, and the general dynamic load test includes impact, natural frequency, dynamic deflection, pulsation, and dynamic strain tests; Static load tests include static deflection and static strain tests. The above-mentioned project owners will choose to conduct partial or complete tests based on specific circumstances, and may add other projects for testing if necessary.
4. According to the test results, if the structure or any part of the structure cannot meet the requirements of the drawings due to construction reasons, the contractor shall carry out reconstruction or reinforcement, and the cost of reconstruction or reinforcement of the structure shall be borne by the contractor.